Wednesday, January 18, 2006

Closets installed, siding

Tailored Closets is here today to install closet systems in master and entry.

Chris from EKView is back to fix downspouts, paint the trim around garage and louver in front, and caulk windows.

Monday, January 16, 2006

Cleaners

Cleaners here today.

Low voltage finishing up - installing punch down block. Tony says vac is $1200-1500 ($400 rough-in only), intercom $1200-1500, security $500. Also, on next house, he said to call him before brick so he can put up doorbell box.

Thursday, January 12, 2006

Closets, etc.

Met with the Tailored Closet woman today. Removed drawers and went back to white - approx $2500.

Todd came by to work on the dishwasher drain and a couple other misc things.

Painter doing touch up.

Garage door guys returned to add keypad and adjust doors.

Monday, January 09, 2006

Wraping up

Electrician finishing today. Trimmer coming today/tomorrow for minor work. Painter back later this week. Cleaning svc Friday?

Friday, December 30, 2005

Garage doors stained

Thursday, December 29, 2005

Plumber

Back to wrap up some final details and test.

Thursday, December 22, 2005

Carpet installed

Also cabinet guy back to put on door hardware and glass

Monday, December 12, 2005

Appliances

Abt showed up today. Stove and hood are backordered. Couldn't install anything since no electrical yet. Also a couple other installation issues.

Sent punch list to DR and JR.

Saturday, December 03, 2005

Plumber

Plumber back to install fixtures etc.

Friday, December 02, 2005

Granite done

Last piece installed. They need to clean up the seams in the master.

Wednesday, November 30, 2005

Low voltage

Low voltage guy finsihed installing intercom system etc.

Granite

Granite guys are supposed to come back with last kichen piece today.

Realized we can't do backsplash until hood is in. Abt coming this week for a walkthrough.

Tuesday, November 29, 2005

Backsplash

Picked up backsplash tile today.

Shower door

Glass guys here to install shower door. Mirrors later this week.

Monday, November 28, 2005

Electrician

Still not done. Will come back once backsplash is installed.

Thursday, November 24, 2005

Lights

Outside garage lights are too small. Had the electrician pull them down. Put one on back garage door and returning 2 others. Ordered new lights like front door light. Missing original fixture for back garage door.

Monday, November 14, 2005

Trimmer, Granite

Trimmer back to install door hardware. Was ready to put in final trim but the shoe was not painted. Painter coming back today.

Granite guy measure and took granite order. Same as washington.

Wednesday, November 09, 2005

Electrician starts

Pulls some wire and installs a few fixtures. Put wrong drop rod on BR2 fan.

Monday, November 07, 2005

Cabinets

Cabinets arrive and installation begins

Friday, November 04, 2005

Tile wraps up

Tile guys finished up

Tuesday, November 01, 2005

Lights

First order of lights arrived today

Friday, October 28, 2005

Sod

Landscapers laid sod today.

Wednesday, October 26, 2005

Landscapers, etc.

Landscapers started today.

They will take the fence down and put it in the garage. City confirmed that once final grading on the parkway begins, you no longer need the fence up.

Hardwood floor guys are staining and putting first coat on.